Al Qarayen TSE Pumping Station Upgradation & Construction 

The Challenge

Sharjah Municipality faced increasing irrigation demand in Al Qarayen. The existing treated sewage effluent (TSE) pumping station and reservoir could no longer handle peak loads or future expansion needs. At the same time, the system had to remain operational during the upgrade, meaning any downtime had to be minimal.

Client

Sharjah Municipality

Industry

Municipality

EPC Contractor

Gulf Water Treatment CO. LTD

Location

Bedea STP Plot, Sharjah, UAE

Purchaser

Sharjah City Municipality

GWT Solution

Gulf Water Treatment was entrusted with designing and executing a comprehensive upgrade to modernize the pumping station and construct a new TSE reservoir.

The upgraded station was designed to deliver a daily capacity of 60,000 m³, integrating advanced pumping, electrical, and automation systems. Four high-capacity pumps were installed in a duty/assist/standby configuration, ensuring resilience while allowing efficient operation under variable demand.

A new compressor-type surge vessel was introduced to protect the network against pressure shocks, and the station’s electrical and automation backbone was completely renewed. A modern MCC and PLC system was constructed to meet utility requirements, equipped with UPS backup and integrated into Sharjah’s central SCADA network for real-time monitoring and remote control.

Civil works were carefully planned to avoid prolonged service interruptions, with temporary bypass arrangements and phased construction. This included new foundations, selective reservoir modifications, and dedicated transformer and MCC rooms. The project strengthened connectivity to Sharjah’s irrigation network through integration of existing and new pipelines, providing a flexible backbone for future expansion.

Scope of Work

The project involved a complete upgrade of the Al Qarayen TSE pumping station, combining civil enhancements, mechanical upgrades, and electrical & automation modernization to deliver a reliable, future-ready system.

Key elements included:

  • Retention and reinforcement of the existing 3,000 m³ reservoir, plus construction of a new TSE reservoir.
  • Installation of four high-capacity duty/assist/standby pumps with surge protection systems.
  • Construction of new MCC and transformer rooms under SEWA standards.
  • Deployment of PLC-based automation with UPS backup and SCADA integration for remote monitoring.
  • Selective civil modifications and epoxy flooring in operational areas for durability.
  • Integration of new DN800 rising main with the existing DN450 irrigation line to strengthen network connectivity.
  • Execution under strict time windows to ensure minimal service disruption during works.

Our Approach

Our approach was built on balancing technical excellence with operational continuity. We prioritized minimizing disruption to Sharjah’s irrigation network while delivering a system that is robust, efficient, and scalable. By combining careful planning, close coordination with municipal authorities, and advanced engineering solutions, the project was completed to international standards—strengthening the reliability of Sharjah’s TSE infrastructure for years to come.

Key Benefits

  • Increased Capacity: Designed to meet current and future irrigation demand (60,000 m³/day).
  • Operational Reliability: Duty/standby pump arrangement and surge protection ensure continuous operation.
  • Digital Control: Remote monitoring and control via SCADA and 4G integration.
  • Future Ready: Infrastructure upgrades allow expansion without major disruption.
  • Minimal Downtime: Works executed within tight shutdown windows, keeping the system functional.

Let’s Connect

Need help with a project, have a
question about our work? We’re here.